Our dream home, the building experience.
On Monday, April 6th, Alpine Insulation was here to start insulating our house. Super nice guys. With just a few hours into it they seemed to have accomplished so much. Little did I know that it would take the rest of the week to… Continue Reading “Insulation!”
In the beginning of March 2020 the Covid-19 took over our lives. The ‘Stay At Home’ act was set in place here in Wisconsin meaning those that were not running an essential business were to close their doors. Those employees were laid off and… Continue Reading “March Updates… even through a pandemic”
Things have been coming along quite nice…weather permitting. With multiple snow falls, we had to contact a company that would specifically do a gravel driveway as most plowing companies don’t want to work on gravel as it dings up and dulls their plow blades.… Continue Reading “Progress at the homestead..”
So things have been moving slowly now as we needed to wait for WeEnergies to bring in the utilities. Once that gets brought in and hooked up…WE WILL HAVE ELECTRICITY!!! Which means the ball will start rolling again. Well, on January 28th I took… Continue Reading “It’s Electrifying!”
We stopped by the house this weekend (1/5/2020) to figure out measurements for two niches that we want incorporated into the wall at the entrance and the bedroom entrance to protect the artwork that we plan to put up in them. While there, we… Continue Reading “Those extra things…”
On November 18th, we sat down and met with the new cabinetry company of Amish Custom Made. I didn’t take any pictures during our meeting as I wanted to respect their culture. Jonas and Chester were super nice. Stacey (super sweet and very creative)… Continue Reading “Winter Update”
On Saturday, November 16th, the roofers started working on the roof. PROGRESS! We pre-apologized for the work they had ahead of them due to our very steep roof lines and multiple valleys they had to deal with. The foreman giggled and said he liked… Continue Reading “The ROOF…”
It’s November 11th and realized I hadn’t posted anything in a while and for good reason. This is when progression slows down. However, an early snow fall on October 31st really threw everyone for a loop. Weather like this can put projects back which… Continue Reading “And now the slow part…”
This week the carpenters were working what seemed to be 24/7. Windows were in, archways put up, roof line completed AND the septic was put in. We visited the house twice over the weekend. The first time to see the progress and the second… Continue Reading “October 21 – 25”
Things are moving along and each time we go to visit, there is a large chunk of work done. These carpenters are working their butts off! Not much to say except for when we visited on October 20th. Check it out. October 14th October… Continue Reading “October 14 – 20th”